Project GP Krk PLC

Project details

Improving energy efficiency and reducing greenhouse gas emissions at the Kukuljanovo concrete plant

 

Investment value: 1.161.916, 83 kn

 GP Krk PLC in order to improve energy efficiency and increase the share of renewable energy sources, the project will implement 1 energy renewal measure technological measures and other interventions in the production / work process that result in a reduction of energy consumption and contribute to the energy efficiency of the process, which will result in energy efficiency through energy savings of 86,770.00 kWh. The implemented measure will contribute to the achievement of the project goal: the overall reduction of energy in the cost unit by 52.03%, compared to the existing situation, as well as the reduction of CO2 emissions of 18.12759 tCO2 / year.

Development of this Web application was co-funded by the European Union, from the European Regional Development Fund. Read more about the project here.